A kitchen renovation in Vancouver takes 4–12 weeks depending on scope. Cosmetic updates: 1–2 weeks. Mid-range renovation: 4–6 weeks. Full gut renovation: 8–12 weeks. Add 2–4 weeks for permit approvals.
One of the first questions homeowners ask about a kitchen renovation is "how long will it take?" The honest answer depends on the scope, but here are realistic timelines based on our experience in Metro Vancouver.
Kitchen Renovation Timeline by Scope
Cosmetic Refresh (1-2 Weeks)
Mid-Range Renovation (4-6 Weeks)
Full Gut Renovation (8-12 Weeks)
The Hidden Time Costs
Pre-Construction (2-8 Weeks)
During Construction
How to Keep Your Renovation on Schedule
SturdyBee Kitchen Renovations
SturdyBee Property Solutions manages kitchen renovations from planning through completion across Metro Vancouver. Our transparent communication means you'll always know where your project stands.
Call (604) 366-4087 for a free consultation and timeline estimate.
People Also Ask
What takes the longest in a kitchen renovation?
Custom cabinetry (4–8 weeks lead time), countertop fabrication (2–3 weeks), and permit processing (2–4 weeks). Plan these well ahead to avoid delays.
Can I use my kitchen during a renovation?
During a full renovation, no — your kitchen will be unusable for 4–8 weeks. Set up a temporary kitchen with a microwave, toaster oven, and cooler in another room.
How can I speed up my kitchen renovation?
Order materials and appliances early, finalize all design decisions before demo begins, and hire an experienced team that manages the full project in-house.